Slab pour at Armstrong’s Dealership.
The 18th Jan saw the first of two main slab pours – 96m3 of concrete came onto site in 17 concrete trucks to pour a slab area of 578m2. After this we’ll have some final ours for the civil ground works exterior, and the MAHA put casettes for the car service pits. We’re targeting the start of Feb for the next pour, aiming to make the most of the sunshine!
Outside of concrete, the site is racing along with the roofing underway and cladding soon to follow to begin closing in the building as we look to start internal framing very shortly.
Other Recent News
September 23, 2026
Giving back to our industry at Farmer Cresent site
September 15, 2026
From foundations to frames: Kāinga Ora Fantame St takes shape
August 20, 2026
A new chapter begins in Cannons Creek
August 19, 2026
A burger-fuelled team
August 13, 2026
Floor by Floor: Drifter takes form
Other Recent News
September 23, 2026
Giving back to our industry at Farmer Cresent site
September 15, 2026
From foundations to frames: Kāinga Ora Fantame St takes shape
August 20, 2026
A new chapter begins in Cannons Creek
August 19, 2026
A burger-fuelled team
August 13, 2026
Floor by Floor: Drifter takes form