Slab pour at Armstrong’s Dealership.
The 18th Jan saw the first of two main slab pours – 96m3 of concrete came onto site in 17 concrete trucks to pour a slab area of 578m2. After this we’ll have some final ours for the civil ground works exterior, and the MAHA put casettes for the car service pits. We’re targeting the start of Feb for the next pour, aiming to make the most of the sunshine!
Outside of concrete, the site is racing along with the roofing underway and cladding soon to follow to begin closing in the building as we look to start internal framing very shortly.
Other Recent News
February 25, 2026
Practical Completion achieved for Paperscape
February 23, 2026
Raft slab milestone at CareVets & Apartments
February 18, 2026
Progress in motion at The Eye Clinic
December 18, 2025
Amazing efforts during the Aoraki Spring into Summer Challenge!
December 16, 2025
Demolition complete at CareVets & Apartments site
Other Recent News
February 25, 2026
Practical Completion achieved for Paperscape
February 23, 2026
Raft slab milestone at CareVets & Apartments
February 18, 2026
Progress in motion at The Eye Clinic
December 18, 2025
Amazing efforts during the Aoraki Spring into Summer Challenge!
December 16, 2025
Demolition complete at CareVets & Apartments site