Progress in motion at The Eye Clinic

With a new roof overhead, a re-strengthened structure, and all internal framing wrapped up last year, the transformation on site is seriously gaining pace. First-fix services are now complete, linings are nearly finished throughout, and plastering is well underway.  It’s already been a busy start to the year.

The lift is just weeks from completion, the main stairs are close behind, and the building is really starting to reveal itself. Next up, the fun part: interior finishes and second fix.

Huge thanks to all our subcontractors who are doing a great job keeping up with the various design changes while bringing smart, practical solutions that keep everything moving forward!