Te Kura Māori o Porirua

392 Warspite Ave, Porirua

Starting on site at Te Kura Māori o Porirua on their hall structural strengthening and interior refurbishment works was a great way to kick off 2024!

The structural strengthening will involve new concrete footings, and the erection of steel columns and beams to form portals, installation of a 12mm structural ply diaphragm and steel angles.

The interior works include new GIB ceilings and acoustic ceiling tiles over the structural ply diaphragm, and new toilets, universal bathroom and hall foyer. As with many school projects, this will also involve the removal of asbestos before any other construction work can be undertaken, something which we are well versed in.

The entirety of the works involves working in close proximity to operational teaching buildings, and being sensitive to the School environment which is at the forefront of our scheduling and day to day operations.

Project Manager

Aaron Worthy

Quantity Surveyor

Emma-Jane Kortegast

Site Manager

Rowan Worthy

PROJECT INFO

Commenced: January 2024

Completed: June 2024

$1.5M

Hall strengthening and refurbishment

Architect: TEAM Architects

Client: Te kura Māori o Porirua Board of Trustees