22nd May 2020
The end of this week saw level 1 poured, the ground floor drainage approved, the ground floor being backfilled and compacted, and scaffolding start to go up on the North Eastern side of the building!
​
July 2021 - Structure takes shape!
The last level 3 slab pour area, pre-pour!
Monark from a distance! The tower crane is holding up a panel up whilst the props are connected to take over and hold it up.
29th May 2020
10/10 would do this week again! The end of this week saw Level 4 steel in place and comflor go down. Level 1 framing on the balconies began which allows for the framing to start after this. On ground floor the retention tanks have been installed as well as the drainage, and footings and edges prepped for the ground floor pour!
What a beautiful day to lay comflor! Our steel riggers are nailing down the comflor to prepare it for the slab reinforcing.
Here we can see the balcony steel in place, as well as the formwork on the ground floor for the slab footings and edges.
With the balcony steel in our carpenters have now begun framing the balconies and the edge of the building!
The steel riggers working from their tag lines torquing and fastening the steel in place for level 4.
All of the stormwater retention tanks are in place on the ground floor, waiting to be submersed in concrete.
With the lift shaft steel in place, we were able to pour around the final columns!