First residents move back into Herbert Gardens
In mid-August, we celebrated the successful handover of Levels 12 and 13. A huge thank you to our site team, sub-contractors, consultants and our client for their hard work in ensuring the apartments were completed to a high standard and ready for residents to return to. This
was a significant milestone in the project, and it would not have been possible without the dedication and commitment of everyone involved.
We are now busily working on another 7 levels, carrying out asbestos removal, demolition, structural strengthening, new mechanical and fire services, new ceilings, floor finishes, and painting and decorating. With the start of Spring, we are (hopefully!) moving into some better
weather as we continue our weathertightness improvements and painting works across the building exterior.
A quick snapshot of what we are up to on site this week:
• Reinstatement and finishing works on Levels 11 and 10.
• Ceiling framing and new building services on Levels 9 and 8.
• Demolition and structural steel installation on Levels 7 and 6.
• Asbestos removal on Levels 5 (and soon to be 4).
• Weathertightness improvements and painting works across all 4 elevations (and the roof), from Level 13 down to Level 7.
We’re excited to deliver another 2 levels back to our residents very soon, marking yet another milestone as we steadily work our way down to
the ground floor.