WHAT'S HAPPENING AT MONARK

Nov 2020 - New Crane on the Block!

There's a buzz of excitement on the site now that our crane is up and fully operational! It signals another new phase of construction, and we can now concentrate on getting ready to pour the ground floor raft slab.  

The ground floor raft slab will be poured in three sections. The first is scheduled to be poured by the end of the month. In preparation for this we have been focusing on completing the inground services, with our reinforcing steel fixers following close behind tying the mammoth volume of steel in the raft slab. The second section is due to be poured in December, and the third and final section is due to be poured in the New Year.

While preparing for our first section raft slab to be formed we are also working on forming the lift pit on site, as well as completing services infrastructure work out on both King Street and Adelaide road.

Show More

Oct 2020 - Preparing for our Crane

One of our first major milestones has now been met - the piling is complete! Brian Perry Civil did a great job and have now de-camped, leaving the site looking quite different to before they arrived.

 

Out on Adelaide Road,  G.P. Friel have been busy installing the underground services to service the new apartment building, including new storm water manholes on Adelaide Road - quite a challenge on such a high volume traffic area.

 

The next major will be getting our crane up, and to that end we have been busily preparing the crane base. The crane base makes clever use of the building's foundations and will therefore remain in place once the crane has been removed. Our crane will have the capacity to lift up to 24 tonnes so that it be able to handle the large precast panels on our project, and will stand approximately 10 storeys high in order for our 3 storey precast panels to be lifted over the top of the building as we progress through construction. 

Show More

Installation of reinforcing steel for the formation of our crane base is underway.

Completed crane base being stripped of form work.

Installation of the cast in crane anchors complete with jig to ensure the position of the anchors suits the soon to be installed crane tower sections.

Tying the reinforcing steel for the crane base.

Sept 2020 - Piles, piles, and more piles!

The focus over the last few weeks has been piling, and with ~160 piles to get in this is no small job. There is quite a high variability in how easy/hard each pile is to drill, and so far they have ranged from taking about 8 minutes to 2 hours to drill a single pile. In brief, for each pile a 13m deep hole is drilled, filled with concrete, and then reinforcing set into it. Check out the reinforcing being driven into the concrete (click here!) - its quite mesmerising!

Despite some  obstructions being encountered, Brian Perry Civil are putting in a great effort and progressing well - we're on track to have piling completed in early October. 

Towards the end of last week, GP Friel were working on Adelaide Road excavating for and installing storm water manholes and we started preparing the ground for the crane base/slab, which will soon have reinforcement put in and tied between 6 piles.

Show More

Pile cages are laid out/stored between drilled/completed piles (the plastic caps are there for safety reasons).

Excavating around the 6 crane base piles to make room for reo and concrete, which will form the crane base slab.

Scaffold has been erected in the crane base area to allow for breaking out of concrete.

Fully excavated crane base area, which has reached the water table!

Freddy's Concrete Cutters breaking out concrete from the lower area of piles for the crane base.

Freddy's Concrete Cutters breaking out the top of the crane base piles, so that reinforcement for the crane base slab can be tied to the pile cages.

Aug 2020 - We are GO!

It's been a busy two months since we signed on to deliver the Monark Apartment development in June; the building that was on site has come down and been removed, our team have moved onto site, extensive groundworks have been completed to prepare the ground, services are in the process of being re-routed, and piling has commenced (3 completed, ~157 to go!) 

Show More

The team have arrived! Site office is in place and the the site has been cleared ready for the next stage.

It's getting busier on site now as Brian Perry Civil get stuck into work on the piling.

For each pile, a hole must be drilled, filled with concrete, and reinforcing driven down to a depth of 13m.

Preparing the ground before the team even moved onto site.

The view from Adelaide Rd prior to work commencing! 

The old building at King St prior to demolition.

CONTACT

If you have property, development or construction needs, or know someone who does, we would be delighted to hear from you!

Chris Goldsbury

Director & General Manager

chris@aorakiconstruction.co.nz

Tel: 027 675 2862

Nigel Butt

Director & Commercial Manager

nigel@aorakiconstruction.co.nz

Tel: 021 227 6262

hiclipart.com.png