2 OCTOBER 2020

As work continues at varying stages on each floor, this week we celebrated Schindler Lifts joining the other contractors working on site. They will now begin work to get our lift in and operational!

Show More

Steel stud partition walls are now being installed on Level 4.

Level 6 is now fully covered and being prepared for steel studs to start going up.

While one side of the hallways are lined, the other side is left open for the service risers.

The elevator shaft is being lined in preparation for installation of the lift!

The roof is continuing to progress and is on track to be completed by the end of the month.

The external precast panels have had their final coat of paint and are looking great!

CONTACT

If you have property, development or construction needs, or know someone who does, we would be delighted to hear from you!

Chris Goldsbury

Director & General Manager

chris@aorakiconstruction.co.nz

Tel: 027 675 2862

Nigel Butt

Director & Commercial Manager

nigel@aorakiconstruction.co.nz

Tel: 021 227 6262

hiclipart.com.png