28 AUGUST 2020

The main focus of this week has been to install the base tray for the roof and to start the facade system install. Alongside this the final stairs were installed and work continued on getting the internal partitions up. Its all go!

The GIB weatherline on our wing walls has reached level 5. We can install it before the building is closed in as it is designed to be able to get wet.

The timber framing for the roof channel has begun, alongside the roof tray going down.

The lift shaft steel is now installed and ready for the base tray.

We have begun to install the spanlock facade panels (in black) on the south side of the building. 

The base layer of the roof tray is currently being installed. This will be closely followed by the vapour barrier.

In the background, our crane is installing our last staircase!