9 OCTOBER 2020

The lower floor apartments are really taking shape now, particularly our showroom apartment. Its exciting watching this one come together, and gives a real feel for what the finished space will be like.

Wellington has put on another great week of weather this week, enabling the roofers and cladding installers to make fantastic progress!

An apartment crammed with insulation! This will soon be installed in the ceiling before the linings go on.

Bathroom tiling is well on its way in our showroom apartment, Apartment 108. 

More glass arriving for Level 6 - there wont be many more of these to come as almost all of the glass is now in!

Level 6 windows and doors are now in. The effects of our Wellington wind will now be massively reduced!

Also on Level 6, services and risers are now being installed.