22nd May 2020
The end of this week saw level 1 poured, the ground floor drainage approved, the ground floor being backfilled and compacted, and scaffolding start to go up on the North Eastern side of the building!
July 2021 - Structure takes shape!
The last level 3 slab pour area, pre-pour!
Monark from a distance! The tower crane is holding up a panel up whilst the props are connected to take over and hold it up.
24 January 2020

Full Name
January 24, 2020
Achievements; plinths boxed and cast in plates set, lift pit, temporary site expansion for steel storage
This week much work was done on the plinths - boxing, setting plates and bolts in concrete. And the lift pit was framed up and concreted. We also